Project/System ID Number: 145

Item Name Information
System Name : Construction of 90.25 MWp (68.60 MW AC) Solar Photovoltaic Grid Connected Power Plant at Gangachara, Rangpur
System ID : SID # 145
Technology Type : Solar Park
Grid Status : On Grid
Capacity : 90.25 MWp
Completion Date : 2022-12-21
Present Status : Under Planning
System Owner : Bangladesh Power Development Board (BPDB) (7)
EPC : Not Found
Financing Org. : Government of Bangladesh (GoB)
Inserted by : Tapos Kumar Saha (31)
Creation Date : 2016-09-22 15:10:27
Updated by : Naznin Nahar Nipu (83)
Modification Date : 2021-11-22 23:33:55
Item Name Information
Implementing Agency : Bangladesh Power Development Board (BPDB)
Office/Program : -
PD Name : Mr. Md. Golam Mortuza
Division : Rangpur
District : Rangpur
Upazilla : Gangachara
Location : Gangachara
Latitude, Longitude : 25.855922, 89.221412
Note : .
Expected Energy Generation and CO2 Emission reduction during System Life : 2 TWh, 931 k tCO2
Expected Energy Generation and CO2 Emission reduction till today : 49 GWh, 23 k tCO2
 